LEAD TIMES
Current casting lead time requirements for non value added castings varies based on mold size. If you are uncertain about the mold size for a particular casting, please contact us.
Updated: Tue Sep 26, 2023
DUCTILE IRON
Mold Line: | "Hunter-10" | "Hunter-20" | "SPO" |
Mold Size: | 14" x 19" | 20" x 24" | 32" x 44" |
Casting Lead Time: | 18 weeks | 20 weeks | 20 weeks |
HIGH CHROME ABRASION RESISTANT WHITE IRON (YC)
Mold Line: | "Hunter-10" | "Hunter-20" | "SPO" |
Mold Size: | 14" x 19" | 20" x 24" | 32" x 44" |
Casting Lead Time: | 22 weeks | 22 weeks | 22 weeks |
GREY CAST IRON
Mold Line: | "Hunter-10" | "Hunter-20" | "SPO" |
Mold Size: | 14" x 19" | 20" x 24" | 32" x 44" |
Casting Lead Time: | 22 weeks | 22 weeks | 22 weeks |
CARBIDIC AUSTEMPERED DUCTILE IRON (CADI)
Mold Line: | "Hunter-10" | "Hunter-20" | "SPO" |
Mold Size: | 14" x 19" | 20" x 24" | 32" x 44" |
Casting Lead Time: | 22 weeks | 22 weeks | 22 weeks |
Due to heavy demand for castings with large cores, if your castings require cores made on our Laempe LB25 core cell the lead time is currently 18 weeks while we work to adjust our production schedule.
Should your castings require additional value added services such as machining, painting or austempering, please allow the "Value Added Lead Time" as noted below in addition to the "Casting Lead Time".
Value Added Service: | Painting/Coating | Machining* | Austempering** |
Value Added Lead Time: | 2 weeks | 4-6 weeks | 4 weeks |
* Machining lead time includes painting/coating if applicable
** Austempering lead time includes transit time to heat treatment plant.
Sign up for updates on lead times via email.