Updated: Monday July 13, 2026

DUCTILE IRON & AUSTEMPERED DUCTILE IRON (ADI)

(ASTM A536 – 84 & ASTM A897 – 06)
Moulding LineHunter-10Hunter-20SPO
Mould Size14″ x 19″20″ x 24″32″ x 44″
Casting Lead Time5 weeks7 weeks6 weeks

HIGH CHROME ABRASION RESISTANT WHITE IRON

(ASTM A532 Class III Type A)
Moulding LineHunter-10Hunter-20SPO
Mould Size14" x 19"20" x 24"32" x 44"
Casting Lead Time9 weeks9 weeks9 weeks

CARBIDIC AUSTEMPERED DUCTILE IRON (CADI)

Moulding LineHunter-10Hunter-20SPO
Mould Size14" x 19"20" x 24"32" x 44"
Casting Lead Time26 weeks26 weeks26 weeks

**Due to a drop in CADI demand, we will be holding incoming CADI orders until we have enough demand to justify a full shift of production. When any order for CADI is received we will reach out to all customers that order CADI to request their anticipated usage, and will do our best to provide an estimated delivery date based on that feedback.**

VALUE ADDED SERVICE

Should castings require additional value-added services, please add the below value-added lead times to the production lead time:

Value Added ServicePainting/CoatingMachining*Austempering**
Value Added Lead Time2 Weeks4-6 Weeks5 Weeks

 

* Machining lead time includes painting/coating if applicable

** Austempering lead time includes transit time to heat treat facility.